斜拉桥索塔钢锚梁安装施工工法
目 录<?xml:namespace prefix="o" ns="urn:schemas-microsoft-com:office:office">
1.前言............................................................................................................................. 1
2.工法特点..................................................................................................................... 1
3.适用范围..................................................................................................................... 2
4.工艺原理..................................................................................................................... 2
5.施工工艺流程及操作要点......................................................................................... 2
5.1钢锚梁安装总体工艺....................................................................................... 2
5.2操作要点........................................................................................................... 4
5.2.1施工准备................................................................................................. 4
5.3钢锚梁安装工艺............................................................................................... 5
5.3.1.钢锚梁安装工艺优化改进................................................................... 5
5.3.2 钢锚梁运输、组拼和连续预拼........................................................... 7
5.3.3首节钢锚梁安装..................................................................................... 8
5.3.4其他(标准)节段钢锚梁安装........................................................... 11
5.3.5 钢锚梁安装测量控制.......................................................................... 12
5.3.6钢锚梁安装精度控制........................................................................... 12
5.4劳动力组织..................................................................................................... 15
6、材料与设备............................................................................................................ 15
7、质量控制................................................................................................................ 16
7.1 钢锚梁安装精度保证措施............................................................................ 16
7.2 钢锚梁吊装过程中成品质量控制................................................................ 16
8.安全措施................................................................................................................... 16
8.1船舶安全......................................................................................................... 16
8.2 施工安全操作................................................................................................ 17
9.环保措施................................................................................................................... 18
10.效益分析................................................................................................................. 18
10.1生产周期分析............................................................................................... 18
10.3 经济效益分析.............................................................................................. 19
10.4 社会效益...................................................................................................... 20
11.应用实例................................................................................................................. 20
斜拉桥索塔钢锚梁安装施工工法
编制单位:中交集团第二航务工程局有限公司
1.前言
斜拉桥索塔上塔柱锚固区采用的钢锚梁由受拉锚梁和锚固构造组成,即“钢锚梁+钢牛腿”的全钢结构组合,为业界首创。锚梁作为斜拉索锚固结构,承受斜拉索的平衡水平力,不平衡力由索塔承受,竖向分力全部通过牛腿传到塔身;空间索在面外的水平分力由钢锚梁自身平衡,使得结构受力更明确。
金塘大桥主桥为双塔双索面钢箱梁斜拉桥,采用全钢结构的钢锚梁作为斜拉索的锚固结构,在国内外尚属首次。由于钢锚梁具有安装速度快、定位精确的特点,从而保证了斜拉索的安装精度。为了将金塘大桥钢锚梁安装的成功经验推而广之,经总结和提炼,制定了本工法,为今后类似结构施工提供参考或借鉴。
2.工法特点
2.1首节钢锚梁(基准节段)安装采用简易支撑支架、限位导向装置、高程调节螺栓并行,操作便捷,并为提高整个钢锚梁的安装精度打下了良好的基础。
2.2根据塔吊的起重能力及塔身钢筋构造,钢锚梁采取单节吊装,安装机动灵活。
2.3采用能适应钢锚梁尺寸变化的可调专用吊具,只需一副吊架,便可完成所有钢锚梁的吊装作业,操作简便,吊装安全可靠。
2.4对钢锚梁的制造、运输和安装三阶段采取全过程的控制,不但能提高钢锚梁的安装精度,而且能加快施工进度。
<?xml:namespace prefix="st1" ns="urn:schemas-microsoft-com:office:smarttags">
3.适用范围
适用于斜拉桥索塔钢锚梁安装施工,对于类似的钢塔安装也可借鉴采用。
4.工艺原理
钢锚梁采取分批次安装,通过分析自然环境(风、日照等)和主体结构(钢筋、混凝土等)的影响,确定每批次钢锚梁安装的节段数。对首节钢锚梁(基准节段)进行精确调位并固定后,浇筑完成该节段混凝土后,陆续吊装后续其他批次钢锚梁(每批次1至2个节段),每一个批次钢锚梁吊装完成后,进行与之对应节段塔柱混凝土的浇筑,依次循环施工直至全部完成。
钢锚梁安装误差采取分批次调整,通过监测已装钢锚梁的实际位置,分析安装误差影响,确定下批次钢锚梁安装时是否需要进行倾斜度调整以及调整量(若需要调整)。
钢锚梁分为首节钢锚梁安装和其他节段钢锚梁安装,钢牛腿是钢锚梁的支撑结构,由座板、托架、塔壁预埋钢板、剪力钉和劲性骨架相连的连接钢板组成。(钢锚梁标准节段结构参见图5.1-1)。